Shanghai Gaosuo Electrical Co., Ltd.
News Center

Company News

Quality Never Compromised Safety Never Compromised

Selection Guide and Installation & Maintenance Key Points for Compact Substations

2 2026-08-17 16:50:00

Whether the selection of a compact substation is reasonable and whether the installation is standard directly affect power supply reliability and equipment service life. This article provides a complete operational guide from capacity selection, equipment configuration, foundation construction to operation and maintenance.

I. Capacity Selection Method

Transformer Capacity Calculation

The capacity selection of a compact substation takes the transformer capacity as the core parameter. The calculation steps are as follows:

  1. Calculate the total calculated load (kW) within the power supply area
  2. Apply a diversity factor (0.7~0.9, depending on load nature)
  3. Convert to apparent power: S = P_total / (power factor × transformer load factor)
  4. Select the standard capacity level: 50, 100, 160, 200, 250, 315, 400, 500, 630, 800, 1000, 1250, 1600, 2000, 2500kVA
  5. Reserve 20%~30% margin for future expansion

Calculation Example

For a residential community with total calculated load of 480kW, power factor 0.9, diversity factor 0.8, and transformer load factor 0.75:

S = 480×0.8 / (0.9×0.75) ≈ 569kVA → Select 630kVA compact substation

II. Transformer Type Selection

Comparison ItemOil-immersed TransformerDry-type Transformer
CostLowerHigher (about 1.3~1.5 times)
Overload capacityStrongRelatively strong
Fire resistanceRequires fire isolationExcellent, suitable for densely populated areas
Noise≤55dB≤65dB
Maintenance requirementRegular oil sample testing requiredBasically maintenance-free
Applicable scenariosOutdoor, industrial parksResidential areas, commercial buildings, underground

III. Foundation Construction Requirements

  • The foundation platform is poured with concrete, with a level and flat surface
  • The foundation should be at least 300mm above the surrounding ground to prevent rainwater backflow
  • The foundation size should be larger than the compact substation base, leaving at least 200mm on each side
  • Embed cable inlet and outlet steel conduits, with diameters meeting cable bending radius requirements
  • The gap between the base and foundation should be sealed with cement mortar

IV. Earthing System

  • Buried ring earthing electrodes around the foundation; burial depth not less than 0.8m
  • Transformer working earthing and lightning protection earthing can share the same earthing system
  • At least 2 earthing conductors should be led from the earthing electrode to the compact substation foundation platform
  • Earthing resistance value ≤4Ω; if soil resistivity is high, add resistance-reducing agents or increase the number of electrodes
  • The metal enclosure of the compact substation and high/low-voltage cabinets should all be reliably earthed

V. Pre-commissioning Inspection

  • Doors open and close flexibly, with intact sealing strips
  • Operating mechanisms are flexible, and electrical interlock functions are normal
  • Main switchgear opening and closing operations are normal
  • Instruments and relay protection operate accurately
  • Busbar connections are tight, and insulation supports are intact
  • Fuse ratings are correct, and settings match the design

VI. Operation and Maintenance Key Points

Routine Inspection

  • Check the enclosure sealing for signs of water ingress
  • Observe transformer operating temperature; temperature control devices should be normal
  • Check whether high- and low-voltage side instrument indications are normal
  • Listen to transformer operating sound (uniform "humming" is normal)
  • Check that enclosure ventilation openings are unobstructed

Periodic Maintenance

  • Conduct preventive tests on surge arresters before the annual thunderstorm season
  • For oil-immersed transformers, perform simplified insulating oil tests every 3 years
  • Clean enclosure ventilation openings and heat sinks quarterly
  • Check tightness of all connection bolts and earthing conductors every six months
  • After multiple opening/closing operations of low-voltage circuit breakers, check contact wear

Post-Severe-Weather Handling

After severe weather such as strong winds, heavy rain, or snow/ice, increase inspection frequency. Check for damage or deformation of the enclosure, water ingress, foundation settlement, etc. If abnormalities are found, address them promptly.